Виконання робіт з капітального ремонту частини вул. Барабашівської (від №1 до №17) в м. Золотоноша Черкаської обл.
UAH682,148.40
including VATfrom Apr 22, 2021, 22:36
until Apr 28, 2021, 00:00
from Apr 28, 2021, 00:00
until May 14, 2021, 18:00
from May 17, 2021, 14:35
until May 17, 2021, 15:02
from May 17, 2021, 15:02
until May 21, 2021, 15:37
from May 21, 2021, 15:37
Pay attention!
00:00 - means the beginning of the day, not its end
Show all important dates
Hide dates
The reason for cancellation of the procurement
Cause
impossibility of eliminating the revealed violations of legislation in the field of public procurement
Explanation
Неможливість усунення порушень, що виникли через виявлені порушення законодавства з питань публічних закупівель. Технічна помилка в назві оголошення закупівлі, а саме: пропущена літера «а» в назві будинку №17.
Document name | Document type | Date of publishing |
Not indicated | May 31, 2021, 13:35 | |
Not indicated | May 31, 2021, 13:34 |
Information about customer
Main contact
Show customer contacts
Hide customer contacts
Items list
№ | Name | Quantity | Delivery | Place of delivery |
---|---|---|---|---|
1 |
Виконання робіт з капітального ремонту частини вул. Барабашівської (від №1 до №17) в м. Золотоноша Черкаської обл.
Code DK 021:2015:
45230000-8 Будівництво трубопроводів, ліній зв’язку та електропередач, шосе, доріг, аеродромів і залізничних доріг; вирівнювання поверхонь
|
Quantity: 1 роботи |
Delivery period:
до Dec 31, 2021
|
Place of delivery: Україна, Відповідно до документації |
Procurement documents
Document name | Document type | Date of publishing |
Not indicated | Apr 22, 2021, 22:39 | |
Procurement documents | Apr 22, 2021, 22:37 | |
Not indicated | May 17, 2021, 15:02 | |
Not indicated | May 17, 2021, 15:02 | |
|
Electronic tender documentation
General information
Description
—
Who confirms
participant
Legal justification
Requirement groups
Вид та умови надання забезпечення тендерних пропозицій
General information
Description
—
Who confirms
winner
Legal justification
Requirement groups
Розмір та умови надання забезпечення виконання договору про закупівлю
Terms of payment
About tender
Show more information
Hide detailed information
Auction history
View
Participants of auction
Documents submitted with the offer
Document name | Document type | Date of publishing |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Not indicated | May 14, 2021, 17:21 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 | |
Compliance confirmation | May 14, 2021, 17:00 |
Decision of the responsible person
Document name | Document type | Date of publishing |
May 21, 2021, 15:24 | ||
Not indicated | May 21, 2021, 15:25 |
Answers to requirements for purchase criteria
Offer
Status
disqualified
Documents submitted with the offer
Document name | Document type | Date of publishing |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Not indicated | May 14, 2021, 16:49 | |
Compliance confirmation | May 14, 2021, 16:48 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 | |
Compliance confirmation | May 14, 2021, 16:47 |
Decision of the responsible person
Document name | Document type | Date of publishing |
May 21, 2021, 15:36 | ||
Not indicated | May 21, 2021, 15:36 |
Answers to requirements for purchase criteria
Offer
Status
winner
Documents submitted with the offer
Document name | Document type | Date of publishing |
Documents confirming of qualification | May 13, 2021, 18:08 | |
Documents confirming of qualification | May 13, 2021, 18:08 | |
Documents confirming of qualification | May 13, 2021, 18:08 | |
Documents confirming of qualification | May 13, 2021, 18:08 | |
Compliance confirmation | May 13, 2021, 18:08 | |
Documents confirming of qualification | May 13, 2021, 18:08 | |
Documents confirming of qualification | May 13, 2021, 18:08 | |
Documents confirming of qualification | May 13, 2021, 18:08 | |
Documents confirming of qualification | May 13, 2021, 18:08 | |
Documents confirming of qualification | May 13, 2021, 18:08 |
Answers to requirements for purchase criteria
Offer
Status
Not consideredUseful links
Public procurements list of the client ДЕРЖАВНЕ ПІДПРИЄМСТВО "СЛУЖБА МІСЦЕВИХ АВТОМОБІЛЬНИХ ДОРІГ У ЧЕРКАСЬКІЙ ОБЛАСТІ"You may be interested
UAH738,550.00 including VAT
ViewUAH1,000,000.00 including VAT
ViewUAH1,235,000.00 including VAT
View